The City of Dawson Creek has two different budget streams: Capital Budget and Operating Budget. The Capital Budget covers Capital Projects which contribute to the growth and sustainability of Dawson Creek, while the Operating Budget covers day-to-day costs of maintaining the city.
The 2025 Capital Budget was approved at the Regular Meeting of Council on January 27, 2025. View the full report online.
Upcoming projects or projects underway will be listed below as information becomes available.
Barbaree Park Storm Outfall |
The storm outfall near the creek at Barbaree Park has begun to collapse. The tender for this project closed on July 11, 2024.
Update October 2, 2024: The construction costs for this project were determined to be unfeasible. Staff have brainstormed a new idea and the work is planned to be deferred to the 2025 Capital Budget. |
Mile 0 Park Society: Pump Track |
The Mile 0 Park Society is a leaseholder of the City-owned land located at Rotary Recreation Park and the Walter Wright Pioneer Village. In August, the society broke ground on an exciting new project: an All Wheels Pump Track. The project includes three different tracks for different skill levels and is part of the society’s plan to revive the Rotary Recreation Park where Rotary Lake was once housed. The lake was a community hub that existed for many generations until 2017 when the lake closed due to the inability to obtain the right to continue operating as a lake from the Northern Health Authority. It is anticipated that the pump track will be ready for use in summer of 2025. |
Visitor Information Centre: Museum Ramp & Concrete Path Replacement |
Crews replaced the paving stone path outside of the Visitor Information Centre through August and September. The accessible ramp leading into the centre entrance is budgeted for 2025. |
8 Street Storm Crossing Replacement Between Traffic Circle and Rail |
The contract for this project was awarded in Fall 2023; however, work was delayed until 2024 with the return of warmer temperatures. Minor work was done in this area to minimize risk until spring of 2024.
Update July 18, 2024: The contractor has completed the pipe replacement, the road and sidewalk repairs, and the landscaping for the culvert crossing replacement near the railroad tracks at 100B Avenue. The next steps for this project include some sidewalk upgrades near the rail crossing upon successful coordination with CN Rail for rail flaggers.
Update October 2, 2024: The contractor has completed the pipe replacement, the road and sidewalk repairs, and the landscaping for the culvert crossing replacement near the railroad tracks at 100B Avenue. A new concrete sidewalk for access to from 8 Street to the NAR Parking lot was completed in September 2024, bringing this project to a close. |
96 Avenue from 8 Street to 13 Street Road Rebuild with Storm, Sewer and Water Upgrades |
The rebuild of 96 Avenue from 8 Street to 13 Street is underway.
Update July 18, 2024: The road surface has been removed on 96 Avenue. Crews are working to replace underground water and sewer utilities before work begins on road base reconstruction. Waterworks changes are complete, and sanitary manhole updates are complete. Storm main upgrades are about 50% complete and sanitary relining remains for the deep utility work.
Update October 2, 2024: Curb, gutter, and sidewalk was installed early September and paving was completed late September. While the road is now open for traffic, the completion of this project is anticipated for October 15, 2024. |
100B Avenue Road Reconstruction |
The design for this project is nearing completion, and the tender is expected to go out in late July. |
112 Avenue from 7 Street to 8 Street Road Rebuild with Water and Drainage Upgrades |
This project is now underway as of June 2024. This project requires a new right of way for water mains along the north flank of the Dawson Creek Safeway.
Update July 18, 2024: The contractor began work on this project on July 8, 2024. The road between Safeway and the Dawson Creek Mall on 112 Avenue has been milled and the Contractor is removing road base for reconstruction. The road is being prepared for asphalt pavement.
Update October 2, 2024: Waterworks and storm works on the 112 Avenue project from 7 Street to 8 Street were complete in August. The road base work is nearly complete, and the community can expect to see curb, gutter, and paving coming throughout the next few weeks. |
2024 Projects |
Facilities & Parks
Road Works, Streetlights and Utilities
|
2023 Projects |
|
2022 Projects |
|
2021 Projects |
|