Skip to main content Skip to footer

Capital Projects

The City of Dawson Creek has two different budget streams: Capital Budget and Operating Budget. The Capital Budget covers Capital Projects which contribute to the growth and sustainability of Dawson Creek, while the Operating Budget covers day-to-day costs of maintaining the city.

The 2025 Capital Budget was approved at the Regular Meeting of Council on January 27, 2025. View the full report online.

Text that says Investing in City Assets and Infrastructure

Where money comes from

  • Carry-forward Capital Reserve
  • Conditional Government Grants
  • Grants from Gas Funds
  • Equipment Pool Reserve
  • Interest
  • Long-term Borrowing
  • Peace River Agreement (PRA)
  • Water and Sewer Infrastructure

Where money goes

  • Airport
  • Drainage
  • Equipment 
  • Facilities
  • Paving
  • Sewer
  • Sidewalks
  • Water 

Current Projects

Upcoming projects or projects underway will be listed below as information becomes available.  

Facilities and Parks

The storm outfall near the creek at Barbaree Park has begun to collapse. The tender for this project closed on July 11, 2024.

 

Update October 2, 2024: The construction costs for this project were determined to be unfeasible. Staff have brainstormed a new idea and the work is planned to be deferred to the 2025 Capital Budget. 

The Mile 0 Park Society is a leaseholder of the City-owned land located at Rotary Recreation Park and the Walter Wright Pioneer Village. In August, the society broke ground on an exciting new project: an All Wheels Pump Track. The project includes three different tracks for different skill levels and is part of the society’s plan to revive the Rotary Recreation Park where Rotary Lake was once housed. The lake was a community hub that existed for many generations until 2017 when the lake closed due to the inability to obtain the right to continue operating as a lake from the Northern Health Authority.  It is anticipated that the pump track will be ready for use in summer of 2025.

Crews replaced the paving stone path outside of the Visitor Information Centre through August and September. The accessible ramp leading into the centre entrance is budgeted for 2025.

Road Works, Streetlights and Utilities

The contract for this project was awarded in Fall 2023; however, work was delayed until 2024 with the return of warmer temperatures. Minor work was done in this area to minimize risk until spring of 2024. 

 

Update July 18, 2024: The contractor has completed the pipe replacement, the road and sidewalk repairs, and the landscaping for the culvert crossing replacement near the railroad tracks at 100B Avenue. The next steps for this project include some sidewalk upgrades near the rail crossing upon successful coordination with CN Rail for rail flaggers.

 

Update October 2, 2024: The contractor has completed the pipe replacement, the road and sidewalk repairs, and the landscaping for the culvert crossing replacement near the railroad tracks at 100B Avenue. A new concrete sidewalk for access to from 8 Street to the NAR Parking lot was completed in September 2024, bringing this project to a close.

The rebuild of 96 Avenue from 8 Street to 13 Street is underway. 

 

Update July 18, 2024: The road surface has been removed on 96 Avenue. Crews are working to replace underground water and sewer utilities before work begins on road base reconstruction. Waterworks changes are complete, and sanitary manhole updates are complete. Storm main upgrades are about 50% complete and sanitary relining remains for the deep utility work.

 

Update October 2, 2024: Curb, gutter, and sidewalk was installed early September and paving was completed late September. While the road is now open for traffic, the completion of this project is anticipated for October 15, 2024.

The design for this project is nearing completion, and the tender is expected to go out in late July.

This project is now underway as of June 2024. This project requires a new right of way for water mains along the north flank of the Dawson Creek Safeway. 

 

Update July 18, 2024: The contractor began work on this project on July 8, 2024. The road between Safeway and the Dawson Creek Mall on 112 Avenue has been milled and the Contractor is removing road base for reconstruction. The road is being prepared for asphalt pavement.

 

Update October 2, 2024: Waterworks and storm works on the 112 Avenue project from 7 Street to 8 Street were complete in August.  The road base work is nearly complete, and the community can expect to see curb, gutter, and paving coming throughout the next few weeks. 

Completed Projects

Facilities & Parks

  • Airport Control Tower HVAC: A new HVAC unit was installed in the Airport Control Tower.
  • Cairn Sign Replacement: In late winter of 2023, the Alaska Highway Cairn Sign located at the traffic circle was removed for refurbishment. The sign received some necessary upgrades to ensure that it will last well in to the future. The upgraded sign was reinstalled in it's original location at the traffic circle on the far northeast corner of the NAR Park parking lot in April 2024. 
  • Calvin Kruk Centre for the Arts HVAC: The HVAC system in the Calvin Kruk Centre for the Arts was nearing failure and required a full replacement. The project began in August, and the units have been installed. The drywall and T-bar repairs finalized through September. This will improve the overall heating and cooling of this large City asset.
  • Dawson Creek Art Gallery Entrance Upgrade: This project began as a design to improve accessibility when entering the Dawson Creek Art Gallery. The vestibule was updated, along with the roofing and the installation of new windows and doors which greatly improved the entrance. The project was completed in November 2024.
  • Decorative Rock Replacement: 

    The decorative rocks around the leisure pool and swirl pool were in poor shape at the Kenn Borek Aquatic Centre (KBAC). Many of them were disintegrating and in need of repair. The project was completed during the 2024 Annual Maintenance Shutdown.

  • Kin Arena Sports Flooring: 

    Sports flooring for the Kin Arena was purchased and was installed summer of 2024 for testing. At the September 9 Meeting, Council approved the temporary testing of the Kin Arena as a "fieldhouse" with sports flooring installed for a one-year trail period. The Kin Arena will house the sport flooring which can accommodate several sports including volleyball, basketball, pickleball, badminton, futsal and more. The second ice surface, in addition to the Memorial Arena, will be the Ovintiv Events Centre (OEC). This is line with Council’s Strategic Priorities and their intention to give the OEC a heavier community-based focus. 

     

    The sport flooring is specifically de­signed for court sports rather than stick sports. It includes the

    following sport lines:

    • Three volleyball courts

    • Eight pickleball courts

    • One basketball court

    • Eight badminton courts

    • Two futsal (indoor soccer) courts

  • Kin Park Accessible Playground: Contractors broke ground at the Kin Park playground site in September 2023 and 90% of the playground equipment was installed before the winter season. In 2024, contractors installed additional equipment, an accessible rubber matting surface, and paved new trail networks connecting the playground to the greater trail system. This playground opened to the public on Monday, June 10, 2024.
  • Kin Park Multi-Use Courts - Creekside Courts: The new multi-use outdoor court facility in Kin Park was open for play as of Wednesday, August 23, 2023. An engagement session was held on September 15, 2023. At the September 9, 2024 Council Meeting, Council approved the naming of the facility as "Creekside Courts". A grand opening ceremony was held on September 25, 2024 and the project is now complete.
  • Kin Park Trail Network Connections: Several new areas within Kin Park have been paved, connecting the new playground and the new multi-use sports courts to the existing trail network. Amenities such as bike racks, benches and tables were installed throughout the south side of Kin Park.
  • Memorial Arena HVAC: The Memorial Arena received a few updates internally, including the BAS HVAC units for heating and cooling the building. 
  • Memorial Arena Pad Replacement: The Memorial Arena Pad underneath the ice was replaced in summer of 2024. Heat floor loops were installed and pressure tested, dasher boards were replaced, and repairs and maintenance were performed on the ice plant. 
  • Rotary Park Playground Upgrade: Contractors broke ground at the Rotary Park playground site in September 2023 and 90% of the playground equipment was installed before the 2023/2024 winter season. By July 2024, the playground construction and landscaping was complete. The new playground was opened for play as of July 15, 2024.

Road Works, Streetlights and Utilities

  • 109 Avenue from 15 Street to 17 Street: Paving of 109 Avenue from 15 Street to 17 Street, including underground utility work, was completed in summer of 2024 and this project is now complete.

  • Camarlo Subdivision Phase 3 Road Rebuild, Drainage Upgrades and Streetlights: The third phase of the Camarlo Subdivision paving project, which included water and sewer upgrades, started in May 2024. The project moved along quickly and the road in the Camarlo Subdivision has now been paved, with landscaping and hydroseeding completed.Downtown Traffic Lights: Staff worked with contractors to replace the downtown traffic lights located at 102 Avenue and 103 Avenue on 10 Street. The lights were in need of some care and attention for some time, and Staff were excited to see this project on the roster for the summer of 2024. The project included:

    • Traffic light pole replacements
    • New accessible ramps
    • Bricks removed, new brushed concrete surface at corners
  • Parkhill Transmission Main Water Line: Crews completed the highway crossings and CN Rail bore crossing required for the Parkhill Transmission Main Water Line. This project was completed in October 2024. 
  • Sanitary Trunk Main Flushing: Flushing of the Sanitary Trunk Main across the City was completed in August. Flushing the main is necessary for regularly upkeep and maintenance of the line. After the flushing, the pipe is cctv’d with a camera to identify any problems areas or issue of concern for future addressing. 

  • Ball Diamond Upgrades
  • Christmas Decoration Upgrades Phase Two
  • Kin Park Multi-Use Outdoor Courts
  • NAR Park and Visitor Centre Lights
  • South Peace Multiplex Building Upgrades and Parking Lot Lights Structural Assessment
  • 14 Street from 102 Avenue to Alaska Avenue Streetlights
  • 17 Street Water Main Repair
  • 95 Avenue from 13 Street to 17 Street Road Rebuild, Drainage Upgrades and Streetlights
  • 96 Avenue from 8 Street to 13 Street Streetlights
  • 102 Avenue Bridge Slope Repair Work 
  • 106 Avenue from 6 Street to 8 Street Sanitary Trunk replacement
  • Arena Water Main Extension
  • Camarlo Subdivision Phase 2 Road Rebuild, Drainage Upgrades and Streetlights

  • 96 Avenue road work from 13 Street to 17 Street
  • Camarlo subdivision road work from 89 Avenue to 20A Street

  • 8 Street Frontage Road from 116 Avenue to 122 Avenue 
  • 8 Street Creek crossing replacement
    • Please note, this was a Ministry of Transportation project, not a City of Dawson Creek project. Questions or concerns may be directed to the Brocor office at 250-782-3404.
  • 10 Street from 92 Avenue to 94 Avenue
  • 10 Street from 110 Avenue to 112 Avenue
  • 13 Street from Alaska Avenue to 102 Avenue

  • 15 Street from 96 Avenue to Alaska Avenue
  • 17 Street from 89 Avenue to 210 Road
  • 102 Avenue Creek crossing replacement

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.