City Projects

The City of Dawson Creek has two different budget streams: Capital Budget and Operating Budget. The Capital Budget covers Capital Projects which contribute to the growth and sustainability of Dawson Creek, while the Operating Budget covers day-to-day costs of maintaining the city.

The 2026 Capital Budget was approved at the Regular Meeting of Council on January 12, 2026. View the full report online.

Where Capital money comes from

  • Carry-forward Capital Reserve
  • Conditional Government Grants
  • Grants from Gas Funds
  • Equipment Pool Reserve
  • Interest
  • Long-term Borrowing
  • Peace River Agreement (PRA)
  • Water and Sewer Infrastructure

Where Capital money goes

  • Airport
  • Drainage
  • Equipment 
  • Facilities
  • Paving
  • Sewer
  • Sidewalks
  • Water 

Current Projects

Upcoming projects or projects underway will be listed below as information becomes available.  

Drainage, Paving, Sewer and Water

About the Project
This project will improve the road surface and grade at the 17 Street CN Rail crossing. Engineering design work is being completed to address safety concerns, improve driving conditions, and reduce long-term pavement deterioration at this important transportation corridor.

The completed design will support future reconstruction work and ensure the crossing meets railway safety and operational requirements.

Estimated Cost:
$50,000

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design

Project Status:
In Progress

Latest Update:
The project is currently in the conceptual design stage. Work is underway to complete the engineering design in 2026, with engagement planned with CN Rail as the project moves forward.

About the Project
This project will fully reconstruct 94 Avenue between 8 Street and 11 Street. Work includes replacing the road surface and upgrading underground water, sewer, and drainage utilities that have reached the end of their service life.

Rebuilding both the road and underground infrastructure together will improve long-term safety, reduce future maintenance issues such as potholes and utility failures, and ensure the corridor is built to current standards.

Estimated Cost:
Out for Tender

Estimated Start:
July 2026

Estimated End:
October 2026

Current Phase:
Tendering

Project Status:
Upcoming

Latest Update:
The project is currently out for tender. Construction is expected to begin following the award of contract, with full reconstruction including road, water, sewer, and drainage upgrades planned for 2026.

About the Project
This project includes the reconstruction of 100B Avenue and a section of Wilson Road, focusing on the corridor east of 8th Street near local business frontages. Work includes road rebuilding, drainage improvements, and underground utility rehabilitation to improve long-term infrastructure reliability in the area.

Additional work is being completed to address underground conditions encountered during construction, including sewer and surface restoration items, to ensure the corridor is fully restored and functions as intended.

Estimated Cost:
$1,600,000

Project Start:
2024

Estimated End:
2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Construction is ongoing in 2026, with remaining sewer rehabilitation and surface restoration work underway. Additional corrective work is being completed to address underground infrastructure conditions encountered during construction, including sidewalk and surface reinstatement, with the goal of delivering a fully restored and functional corridor.

About the Project
This project will complete the rehabilitation of the Arenas parking lot, including grading, base preparation, drainage improvements, and new asphalt paving. The work builds on earlier preparatory work and will deliver a fully renewed, all-weather parking surface for the arena complex.

The upgrades are designed to improve drainage, reduce surface deterioration, and provide safer, more accessible parking for users throughout the year.

Tender Awarded:
$1,299,579.45

Successful Proponent:
Brocor Construction Ltd. 

Project Start:
May 2026

Estimated End:
August 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Grading, base preparation, and underground servicing work are complete, with reconstruction of the parking surface progressing. Final paving and drainage adjustments will complete this phase of the project.

About the Project
This project is improving stormwater drainage in Barbaree Park, located east of 15th Street near the dog park. The work focuses on addressing a failing storm main and improving how water is managed through the park.

The original underground pipe was replaced with a more cost-effective surface drainage solution. This approach improves long-term reliability, reduces the risk of future failure, and allows the area to be restored as a more natural park space.

Estimated Cost:
$466,856

Project Start:
Summer 2024

Estimated End:
October 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Drainage works were completed in 2025 included daylighting the storm main, installing erosion protection, and replacing a small section of pipe. Remaining work in 2026 includes trail re-routing and final landscaping to restore and naturalize the park area.

 

About the Project
This project involves replacing an aging lift station near the BC Hydro corridor to improve the reliability of the sewer system. The new infrastructure will increase capacity, reduce the risk of system failures, and support safe and efficient wastewater pumping operations.

Upgrading this facility is essential to maintaining dependable sewer service for surrounding areas and ensuring the system meets current and future demand.

Tender Awarded:
$2,229,587.00

Successful Proponent:
Infracon Construction Inc.

Estimated Start:
June 2026

Estimated End:
Fall 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Construction is scheduled to begin in June 2026. Work includes full replacement of the existing lift station and associated components to improve system reliability and long-term performance.

About the Project
This project involves detailed condition assessments of 11 bridges within the community. The inspections will help identify maintenance needs, structural issues, and long-term repair priorities to support safe and reliable transportation infrastructure.

The information gathered will be used to guide future repair, rehabilitation, or replacement planning and ensure infrastructure decisions are based on current structural conditions.

Estimated Cost:
n/a

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Planning

Project Status:
Upcoming

Latest Update:
Condition assessments are planned for 11 bridges in 2026. The results will inform future maintenance and capital planning priorities for bridge infrastructure.

About the Project
This project involves the first phase of major road and drainage improvements within the Canalta Subdivision. Work includes roadway reconstruction and drainage upgrades to improve long-term road performance, safety, and stormwater management in the neighbourhood.

The overall Canalta improvements have been divided into multiple phases to reduce disruption. Completing the full subdivision at once would significantly limit property access and create major traffic impacts. Phasing the work allows construction to proceed in a manageable way while maintaining access for residents and minimizing community disruption.

Estimated Cost:
Out to Tender

Estimated Start:
Summer 2026

Estimated End:
October 2026

Current Phase:
Construction

Project Status:
Upcoming

Latest Update:
Phase 1 work is scheduled to begin in 2026 and will focus on key road and drainage corridors within the subdivision. Additional phases are planned for future years to complete the remaining sections of the neighbourhood in a way that maintains access and reduces overall disruption to residents.

About the Project
This long-term project is focused on securing a reliable and sustainable drinking water supply for Dawson Creek and surrounding communities. Work is underway to identify and evaluate future water sources, along with the infrastructure needed to deliver and treat water for residential, business, and industrial use.

View the full project updates at dawsoncreek.ca/water-supply

The project is being advanced in response to increasing drought conditions and long-term pressure on the current water source, the Kiskatinaw River. It includes technical studies, environmental review processes, and engagement with Indigenous communities, residents, and regulatory agencies to determine the best path forward for future water security.

Estimated Cost:
To be determined (multi-phase program)

Project Start:
January 2024

Estimated End:
Ongoing (multi-year program)

Current Phase:
Planning / Environmental Assessment

Project Status:
In Progress

Latest Update:
Detailed technical work is ongoing to assess future water needs, potential new water sources, and infrastructure options to deliver a long-term supply. This work builds on earlier engagement and environmental review steps and will continue through multiple phases before a final solution is selected.

About the Project
This project is implementing a fixed network system for water meter reading. The upgrade allows water meters to transmit usage data automatically, reducing the need for manual meter reads and improving the accuracy and efficiency of billing and water system monitoring.

The system also supports better leak detection and helps improve overall water conservation and operational efficiency.

Project Cost:
$153,834.89

Successful Proponent:
Neptune Technology Group Canada Co.

Project Start:
2024

Estimated End:
2026

Current Phase:
Construction / Implementation

Project Status:
In Progress

Latest Update:
Installation of fixed network components is nearing completion, with additional communication devices being added to expand system coverage. Once fully implemented, the system will allow remote meter readings and improve water usage tracking across the community.

About the Project
This project involves completing the engineering design for a new or upgraded lift station in the Heritage area. The design work will determine how wastewater is collected and efficiently pumped through the sewer system to support reliable service for the surrounding neighbourhood.

The upgraded design will help improve system performance, reduce the risk of failures, and ensure the infrastructure is capable of meeting current and future demand.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design

Project Status:
Upcoming

Latest Update:
Engineering design work is underway to define the layout and requirements for the Heritage Lift Station upgrade. The design will guide future construction and ensure the system is built to meet long-term capacity and reliability needs.

About the Project
This project is the first phase of updating the long-term plan for how wastewater is managed. A new Liquid Waste Management Plan is required to support renewal of the current wastewater permit and ensure future system planning meets regulatory requirements and community needs.

Phase 1 focuses on setting up the foundation for the plan, including forming working groups and beginning engagement with key partners and interested parties.

Estimated Cost:
Not specified

Project Start:
Summer 2025

Estimated End:
Ongoing

Current Phase:
Planning / Engagement

Project Status:
In Progress

Latest Update:
Working groups are being formed to begin early engagement and planning for the first phase of the Liquid Waste Management Plan update.

About the Project
This project involves upgrading programmable logic controllers (PLCs) and related control systems across both the water and sewer systems. These systems are used to monitor and operate critical infrastructure such as lift stations, treatment processes, and distribution controls.

The upgrades will improve system reliability, enhance real-time monitoring, and reduce the risk of equipment failure, supporting more efficient and dependable utility operations.

Estimated Cost:
To be determined

Estimated Start:
Summer 2026

Estimated End:
Fall 2026

Current Phase:
Design / Implementation

Project Status:
In Progress

Latest Update:
Upgrades are underway to modernize PLC hardware and software across both water and sewer systems. Work includes replacement of aging control components and improvements to monitoring and automation systems to support more reliable utility operations.

About the Project
This ongoing program focuses on repairing and renewing paved roads throughout the community. Work includes asphalt patching, surface repairs, and roadway overlays to address deterioration, extend pavement life, and improve driving conditions.

The program targets priority areas identified through road condition assessments to ensure maintenance is completed where it is needed most.

Estimated Cost:
$544,042

Project Start:
April 2026

Estimated End:
October 2026

Current Phase:
Construction / Maintenance Program

Project Status:
In Progress

Latest Update:
The first round of patching has been completed, with a second list of priority locations scheduled for mid-2026. Work continues across identified roads to address surface wear and improve overall roadway condition.

About the Project
This project involved replacing a critical section of the main sewer trunk line between 13 Street and 8 Street. The work improves the reliability and capacity of the wastewater system and reduces the risk of service disruptions caused by aging infrastructure.

The project has reached substantial completion, with final site stabilization and restoration activities continuing to ensure long-term performance of the installed infrastructure.

Project Cost:
To be confirmed

Project Start:
Summer 2025

Estimated End:
2026

Current Phase:
Substantially Complete

Project Status:
Closeout / Warranty

Latest Update:
Construction work was substantially completed in 2025. Remaining items include contractor warranty obligations, including ongoing monitoring and maintenance of restoration areas (such as hydroseeded sections) to ensure successful establishment and final site stabilization.

About the Project
This project focuses on improving stormwater management around the South Peace Community Multiplex site. The work will address how rain and surface water is collected, directed, and managed in the area to reduce pooling, improve drainage performance, and support long-term site functionality.

Engineering and design work is underway to determine the best solution for upgrading the stormwater system and ensuring it can handle current and future demand.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Engineering

Project Status:
In Progress

Latest Update:
Engineering and design work is currently underway to assess stormwater system requirements and develop upgrade options for the Multiplex site. The final design will guide future construction and drainage improvements.

About the Project
This project involves upgrading the back area of Sudeten Hall with new paving and site improvements. The work will address uneven and deteriorated surfaces to create a safer, more functional space for access, parking, and community use.

The improvements will also help reduce ongoing maintenance needs and provide a more durable surface for year-round use.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Tendering

Project Status:
Upcoming

Latest Update:
Design work is nearing completion, with construction planning underway for a full reconstruction of the back area, including paving and surface improvements. Construction timing will be confirmed once tendering is finalized.

About the Project
This project focuses on addressing erosion issues at the Trail Reservoir to protect the reservoir structure and surrounding areas. The work is intended to stabilize vulnerable slopes and prevent further erosion that could impact the long-term integrity of the site.

Improving erosion control will help protect critical water infrastructure and ensure the reservoir continues to operate safely and reliably.

Estimated Cost:
To be confirmed

Estimated Start:
Fall 2026

Estimated End:
2026

Current Phase:
Design

Project Status:
Upcoming

Latest Update:
Design work has been awarded and is underway to identify the most effective erosion control measures. Construction is planned following completion of the final design, with work expected to be completed in fall 2026.

About the Project
This project involves replacing underdrain systems and filter media at the Water Treatment Plant. The upgrades are required to maintain effective filtration performance and ensure the continued delivery of safe, high-quality drinking water.

The work helps extend the life of existing treatment infrastructure and supports reliable plant operations.

Estimated Cost:
To be determined

Project Start:
Spring 2026

Estimated End:
Fall 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Replacement of filter media is underway, with materials on site and installation progressing. Remaining work includes completion of underdrain system replacement and final commissioning of the upgraded filtration components.

About the Project
This project involves rehabilitating sections of sewer infrastructure in the Willowbrook area using a lining method. The work is designed to extend the life of existing sewer pipes without full replacement, reducing the risk of leaks, blockages, and service disruptions.

The lining process helps restore structural integrity inside the pipe and improves long-term system reliability while minimizing surface disruption for residents.

Estimated Cost:
Out for Tender

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Tendering

Project Status:
Upcoming

Latest Update:
The project is out for tender, with contract award expected later in 2026. Once awarded, work will focus on lining existing sewer pipes and completing associated restoration. Additional information will be provided to residents affected.

Facilities, Media and Technology

About the Project
This project involves the purchase of a new airport de-icing unit to support safe winter aircraft operations. The unit will be used to remove ice and snow buildup from aircraft surfaces, helping ensure safe departures and arrivals during winter weather conditions.

The new equipment will improve operational efficiency and support reliable airport service during cold-weather conditions.

Equipment Cost:
$293,194

Project Start:
2026

Estimated End:
2026

Current Phase:
Procurement

Project Status:
In Progress

Latest Update:
Funding of $293,194 has been secured through the BCAAP program. Procurement is underway for a one-person de-icing unit to support winter operations at the airport.

About the Project
This project involves repairing and restoring sections of concrete on the airport runway to maintain safe and reliable operating conditions. The work will address surface deterioration and extend the service life of the runway infrastructure.

These repairs are important to ensure continued safe use of the runway and to reduce the need for more extensive rehabilitation in the future.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Preparation

Project Status:
Upcoming

Latest Update:
Final planning is underway for concrete repairs to damaged sections of the runway. Work is expected to proceed in 2026, focusing on restoring surface integrity and maintaining safe operating conditions for aircraft.

About the Project
This project involves refreshing and improving the Alaska Highway Cairn site, a key historical landmark and visitor feature. The work includes site upgrades such as improvements to concrete surfaces, signage, lighting, and landscaping to enhance the appearance and accessibility of the area.

The upgrades are intended to preserve the site, improve the visitor experience, and ensure the landmark remains a well-maintained point of interest in the community.

Estimated Cost:
To be confirmed

Project Start:
May 2026

Estimated End:
2027

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Concrete work, lighting, and site improvements have been completed. Remaining work includes final signage installation and landscaping, which may be carried into 2027 depending on seasonal conditions.

About the Project
This project involves upgrades to the heating, ventilation, air conditioning (HVAC) system and digital control systems at the Calvin Kruk Centre. The work focuses on improving building efficiency, system reliability, and indoor comfort for users of the facility.

Upgrading the controls system allows for better monitoring and management of heating and cooling systems, helping reduce energy use and improve long-term performance.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Construction

Project Status:
In Progress

Latest Update:
Phase 2 upgrades are underway, focusing on improvements to HVAC systems and building control systems. Work is continuing to modernize system performance and improve operational efficiency at the facility.

About the Project
This project involves the installation of new columbarium structures at both the City Cemetery and Brookside Cemetery. Columbariums provide above-ground inurnment spaces for cremated remains, offering a respectful and accessible memorial option for families.

The addition of these structures will help increase available capacity and support long-term cemetery planning needs.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Procurement

Project Status:
Upcoming

Latest Update:
Design and procurement work is underway for new columbarium installations at both cemetery sites. Installation is planned for 2026 following completion of final procurement and site preparation.

About the Project
This project involves planning for new gateway signage at key entry points into the community. The signage will help create a stronger sense of arrival, improve wayfinding, and support community identity for residents and visitors.

Planning work will identify suitable locations, design concepts, and requirements for future installation.

Estimated Cost:
To be confirmed

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Planning

Project Status:
Upcoming

Latest Update:
Planning work is underway to identify locations and develop design concepts for future gateway signage installations. The project will move into design and implementation in future phases.

About the Project
This project involves upgrades to the curling rink facility, including the installation of a new canopy structure and associated improvements. The work is intended to improve shelter, usability, and overall functionality of the facility for users and spectators.

These upgrades will also help extend the usability of outdoor-adjacent areas and improve comfort during seasonal operations.

Tender Awarded:
$308,102.00

Successful Proponent:
C. Chandler Contracting Celtic Construction Ltd.

Project Start:
May 2026

Estimated End:
2026

Current Phase:
Construction

Project Status:
Underway

Latest Update:
Structural work is underway, including preparation of foundations and supports for the new canopy. The existing canopy structure has been removed, with construction progressing toward installation of the new system.

About the Project
This project involves the restoration and enhancement of the cenotaph located at City Hall. The work is intended to preserve the site as an important place of remembrance while improving its overall condition and appearance.

Improvements will help ensure the cenotaph remains a respectful, well-maintained public space for ceremonies and community reflection.

Estimated Cost:
To be confirmed

Estimated Start:
2026/2027

Estimated End:
To be determined

Current Phase:
Design / Construction

Project Status:
In Progress

Latest Update:
Design work is underway, with construction planned to proceed in phases. Funding has been carried forward and supplemented to complete restoration and site improvements in 2026.

About the Project
This project involves upgrades and completion work on the Dawson Creek Exhibition Association (DCEA) horse barns, in partnership with the Northern Lights College (NLC). The improvements support safe, functional, and modern facilities for agricultural events, rodeos, and community programming.

The work focuses on final systems completion and finishing items to ensure the barns are fully operational and ready for public use.

Estimated Cost:
To be determined

Project Start:
2025

Estimated End:
2026

Current Phase:
Substantially Complete

Project Status:
In Progress

Latest Update:
The project is substantially complete, with remaining work focused on final mechanical and electrical commissioning and finishing items. The facility is expected to be fully operational for upcoming Dawson Creek Exhibition events.

About the Project
This project involves upgrading and standardizing signage across City facilities and parks. The work will improve wayfinding, update aging signage, and create a more consistent and recognizable system for residents and visitors using City-owned spaces.

The improvements will help people navigate facilities and parks more easily while supporting a more cohesive public space identity.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Planning / Implementation

Project Status:
Upcoming

Latest Update:
This project is currently in planning, with work underway to review existing signage and develop updated standards for facilities and parks across the community. Implementation will follow once the plan is finalized.

About the Project
This project involves upgrades and improvements to the Ken Borek Aquatic Centre facility and pool systems. The work is focused on maintaining safe, reliable operations and improving the overall experience for users of the facility.

Upgrades may include building systems, pool components, and supporting infrastructure to ensure the facility continues to meet operational and safety standards.

Estimated Cost:
To be determined

Estimated Start:
August 2026

Estimated End:
October 2026

Current Phase:
Design / Planning

Project Status:
Upcoming

Latest Update:
Planning work is underway to identify priority upgrades required to maintain facility performance and reliability. Detailed scope and scheduling will be confirmed prior to construction.

About the Project
This project involves Phase 2 upgrades to the sports floor at the Kin Arena. The work focuses on improving the playing surface to ensure it remains safe, durable, and suitable for a range of community and sporting activities.

The upgrades are intended to extend the life of the facility and improve the overall experience for users.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Planning

Project Status:
Upcoming

Latest Update:
Phase 2 planning is underway, with work focused on defining the scope of improvements to the sports floor. Construction timing will be confirmed once design and procurement are finalized.

Learn more about the sports floor on our Kin Arena Sports Floor page.

About the Project
This project involves exterior improvements to the City-owned Rimrock Medical Clinic building, including upgrades to exterior finishes, accessibility features, and surrounding site conditions. The work is intended to improve the building’s appearance, accessibility, and long-term durability.

These upgrades will help maintain a safe, functional, and welcoming facility for patients and visitors.

Tender Awarded:
$207,780.00

Successful Proponent:
WL Construction Ltd.

Project Start:
June 2026

Estimated End:
Fall 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Exterior renovation work is underway, including replacement of exterior cladding, upgrades to the accessible ramp, and site improvements such as turf and asphalt resurfacing. Final finishing work will continue through the 2026 construction season.

About the Project
This project involves Phase 4 upgrades to Memorial Arena, focusing on continued improvements to key public areas and facility systems. The work is intended to enhance safety, accessibility, and overall user experience at the arena.

Upgrades build on previous phases and help extend the life of the facility while improving day-to-day operations for users and staff.

Estimated Cost:
To be determined

Project Start:
May 2026

Estimated End:
Fall 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Work is underway on Phase 4 upgrades, including improvements to public washrooms, accessibility features, and finishing works in key areas of the facility. Remaining items will be completed through 2026 construction activities.

About the Project
This project involves landscaping and minor site improvements at Rotary Recreation Park in partnership with the Mile 0 Parks Society. The work includes small-scale upgrades such as landscaping, seating, and enhancements around existing amenities to improve the overall park experience.

These improvements support a more welcoming and functional public space for community use and events.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Construction / Maintenance

Project Status:
In Progress

Latest Update:
Minor landscaping and site improvements are underway, including enhancements around existing park amenities. Work is being completed in coordination with the Mile 0 Parks Society, with finishing items scheduled as seasonal conditions allow.

About the Project
This project involves installing accessibility ramps and decking improvements at the Ovintiv Events Centre. The upgrades are designed to improve safe and inclusive access to key areas of the facility for all users.

The work supports better mobility, safer movement throughout the site, and improved usability for events and community programming.

Estimated Cost:
To be determined

Project Start:
Early 2026

Estimated End:
May 2026

Current Phase:
Construction

Project Status:
Complete

Latest Update:
Accessibility ramping and decking improvements have been completed, improving access to key areas of the Ovintiv Events Centre. Final finishing and site clean-up items are being completed as required.

About the Project
This project involves renewing and replacing trees across parks and public green spaces. The work focuses on maintaining a healthy urban canopy, improving park environments, and replacing trees that have reached the end of their life cycle.

New plantings will support long-term shade, aesthetics, and environmental benefits in key park locations throughout the community.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Procurement / Planting

Project Status:
In Progress

Latest Update:
Tree planting is being planned for multiple park locations, with materials arriving in stages. Planting will take place throughout the 2026 season, depending on weather and site readiness.

About the Project
This project involves Phase 2 landscaping improvements at the playground on 16 Street. The work focuses on completing site finishing elements such as grading, green space restoration, and installation of park amenities to support a safe and welcoming play environment.

These upgrades will enhance usability of the space and ensure the playground area is fully integrated into the surrounding park setting.

Estimated Cost:
To be determined

Estimated Start:
Summer 2026

Estimated End:
October 2026

Current Phase:
Construction / Landscaping

Project Status:
In Progress

Latest Update:
Phase 2 landscaping is underway, including installation of site furnishings such as benches, garbage receptacles, and remaining concrete pads. Tree planting and final green space restoration will follow as seasonal conditions allow.

About the Project
This project involves the installation of a new playground at Elwood Drive (Purple Park). The work includes the delivery and installation of playground equipment along with site preparation, surfacing, and basic landscaping to create a safe and accessible play space.

The new playground will provide an updated recreation area for families and children in the neighbourhood.

Estimated Cost:
To be determined

Estimated Start:
Late Summer 2026

Estimated End:
Spring 2027

Current Phase:
Procurement / Installation

Project Status:
Upcoming

Latest Update:
Playground equipment has been procured, with installation planned for late summer to fall 2026. The playground is expected to be open for public use following completion of installation and final site works, which may be Spring 2027.

About the Project
This project involves the installation of a new playground at Hillcrest Park. The work includes site preparation, installation of playground equipment, safety surfacing, and basic landscaping to create a safe and accessible play space for families.

The upgraded playground will provide a modern, durable recreation area designed for long-term community use.

Estimated Cost:
To be determined

Estimated Start:
Late Summer 2026

Estimated End:
Spring 2027

Current Phase:
Procurement / Installation

Project Status:
Upcoming

Latest Update:
Playground equipment has been procured, with installation planned for late summer to fall 2026. The playground is expected to open for public use following completion of installation and final site restoration, which may be Spring 2027.

About the Project
This project involves the removal of outdated playground equipment and installation of new equipment as part of ongoing playground renewal efforts. The work focuses on improving safety, updating aging play structures, and providing modern, accessible play spaces for families.

The upgrades help ensure playgrounds remain safe, functional, and enjoyable for long-term community use.

Estimated Cost:
To be determined

Project Start:
May 2026

Estimated End:
Fall 2026

Current Phase:
Construction

Project Status:
In Progress

Latest Update:
Old playground equipment has been removed and replacement upgrades are underway. New swing sets and play elements are being installed, with remaining site finishing work scheduled for completion in 2026.

About the Project
The Public Art Policy provides the framework for how public art is selected, funded, installed, and maintained. It ensures a consistent approach to public art that reflects community values, supports local artists, and enhances public spaces.

In 2026, this project will focus on implementing the policy through the launch of a Public Art Advisory Committee, which will help guide decisions on how annual capital funding for public art is allocated.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Implementation

Project Status:
Upcoming

Latest Update:
Work is underway to establish the Public Art Advisory Committee. The committee will provide recommendations on how annual public art funding is allocated and help guide future public art projects in alignment with the adopted policy.

About the Project
This project involves the development of a new splash park as part of expanding outdoor recreation amenities. The splash park will provide a free, accessible water play feature for children and families during the summer months, supporting active living and increasing recreational opportunities in local parks.

The project is being delivered in phases, including planning and engagement, detailed design, and future construction.

Estimated Cost:
$2,950,000 (Growing Communities Fund - grant-funded allocation), as well as additional funds to be determined

Project Start:
2025

Estimated End:
2027

Current Phase:
Design / Procurement

Project Status:
In Progress

Latest Update:
Engagement and design work are underway to determine final location, layout, and features. A design-assist and construction procurement process is also underway to support final design refinement and delivery planning for construction.

Sidewalks/Active Transportation

About the Project
This project involves improvements to trail connections and pedestrian pathways within Chamberlain Park. The work is intended to improve accessibility, safety, and overall usability of the park’s trail network.

Upgrades will help create a more comfortable and connected walking environment for residents using the park.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Planning

Project Status:
Upcoming

Latest Update:
Design work is underway to confirm final trail alignments and improvements. Construction timing will follow once design and approvals are finalized.

About the Project
This project involves installing new lighting throughout Kin Park to improve safety, visibility, and usability during evening hours. The upgrades will enhance access to park amenities and support year-round use of the space.

The lighting improvements are also intended to strengthen connections between pathways and key areas within the park.

Estimated Cost:
To be determined

Project Start:
2026

Estimated End:
Fall 2026

Current Phase:
Design / Procurement

Project Status:
Upcoming

Latest Update:
Design work is underway, with installation planned for 2026. The project includes new lighting along key pathways and park areas to improve visibility and safety. Construction will proceed following final procurement and scheduling.

About the Project
This project involves continued upgrades to downtown street lighting and public realm improvements. The work is focused on improving visibility, safety, and the overall appearance of key downtown corridors.

Improvements will support a more welcoming and vibrant downtown environment for residents, businesses, and visitors.

Estimated Cost:
To be determined

Estimated Start:
2026

Estimated End:
2026

Current Phase:
Design / Implementation

Project Status:
Upcoming

Latest Update:
Phase 2 work is underway, focusing on finalizing lighting locations and completing remaining streetscape improvements along key downtown corridors. Installation will proceed once design and procurement are finalized.

Completed Projects

Drainage, Paving, Sewer and Water

  • 1 Street from 116 Avenue to Highway 2 - Paving
  • 110 Avenue from 15 Street to 17 Street – Drainage, Paving, Sewer and Water
  • 95 Avenue from 8 Street to 13 Street – Drainage, Paving, Sewer and Water
  • Arenas Parking Lot: Phase 1 - Drainage 
  • Lagoon Aeration Lines Replacement
  • Memorial Arena Rear Access Rebuild - Paving
  • Mile Zero Parks Society Misting Pad Water Service
  • Pavement Condition Assessment
  • Road Patching/Overlay
  • Sewer Trunk Main Replacement: Phase 1 - 110 Avenue from 13 Street to 8 Street - to substantial completion

Facilities, Media and Technology

  • Alaska Highway Cairn Refresh
  • Arenas Sound System: Phase 2
  • Calvin Kruk Replacement of Heating and Cooling Units
  • Child Care Facility: Concept & Design
  • City App & Websites: tourismdawsoncreek.com and dawsoncreekeventscentre.com 
  • City Hall Accessible Bathrooms - 3rd Floor
  • Curling Rink Crawl Space & Upgrades
  • Dawson Creek Art Gallery Entrance - Phase 2: Landscaping, Sidewalk and Pathway
  • Dawson Creek Exhibition Association Horse Barns: Permitting & Professional Fees
  • Fire Hall Flooring & Building Upgrades
  • Harry Morrow Diamond 1 Outfield Remediation
  • Kenn Borek Aquatic Centre: Regrout Main Pool, Pool Pilots & Lights
  • Mile 0 Park Society: Rotary Recreation Park Pump Track
  • Kin Arena: Front Entrance, Fire Panel, Electrical & IT upgrades
  • Lighting of City Signs and LED Light Retrofit
  • Main Street Revitalization: Phase 1 & 2
  • Memorial Arena: Lobby Flooring & Pillars, Bathrooms
  • Mile Zero Parks Society: Walter Wright Pioneer Village - Paint Buildings, Decking, Playground Rubber & Path
  • Ovintiv Events Centre: Bowl Lighting & Walking Track Level Carpet Replacement
  • Playgrounds: Harry Morrow Ball Diamonds, 16 Street and Phase 1 Removal & Upgrades
  • RCMP Detachment Security & Building Upgrades
  • Splash Park - Design Phase

Sidewalks/Active Transportation

  • Bus Stop Improvement Program
  • Dawson Trail - 17 Street Connector
  • Street Lighting Upgrade Program
  • Trail Network and Active Transportation Plan
  • Vibrant Downtown - Street Lighting and Beautification Program

Facilities & Parks

  • Airport Control Tower HVAC: A new HVAC unit was installed in the Airport Control Tower.
  • Cairn Sign Replacement: In late winter of 2023, the Alaska Highway Cairn Sign located at the traffic circle was removed for refurbishment. The sign received some necessary upgrades to ensure that it will last well in to the future. The upgraded sign was reinstalled in it's original location at the traffic circle on the far northeast corner of the NAR Park parking lot in April 2024. 
  • Calvin Kruk Centre for the Arts HVAC: The HVAC system in the Calvin Kruk Centre for the Arts was nearing failure and required a full replacement. The project began in August, and the units have been installed. The drywall and T-bar repairs finalized through September. This will improve the overall heating and cooling of this large City asset.
  • Dawson Creek Art Gallery Entrance Upgrade: This project began as a design to improve accessibility when entering the Dawson Creek Art Gallery. The vestibule was updated, along with the roofing and the installation of new windows and doors which greatly improved the entrance. The project was completed in November 2024.
  • Decorative Rock Replacement: 

    The decorative rocks around the leisure pool and swirl pool were in poor shape at the Kenn Borek Aquatic Centre (KBAC). Many of them were disintegrating and in need of repair. The project was completed during the 2024 Annual Maintenance Shutdown.

  • Kin Arena Sports Flooring: 

    Sports flooring for the Kin Arena was purchased and was installed summer of 2024 for testing. At the September 9 Meeting, Council approved the temporary testing of the Kin Arena as a "fieldhouse" with sports flooring installed for a one-year trail period. The Kin Arena will house the sport flooring which can accommodate several sports including volleyball, basketball, pickleball, badminton, futsal and more. The second ice surface, in addition to the Memorial Arena, will be the Ovintiv Events Centre (OEC). This is line with Council’s Strategic Priorities and their intention to give the OEC a heavier community-based focus. 

     

    The sport flooring is specifically de­signed for court sports rather than stick sports. It includes the

    following sport lines:

    • Three volleyball courts

    • Eight pickleball courts

    • One basketball court

    • Eight badminton courts

    • Two futsal (indoor soccer) courts

  • Kin Park Accessible Playground: Contractors broke ground at the Kin Park playground site in September 2023 and 90% of the playground equipment was installed before the winter season. In 2024, contractors installed additional equipment, an accessible rubber matting surface, and paved new trail networks connecting the playground to the greater trail system. This playground opened to the public on Monday, June 10, 2024.
  • Kin Park Multi-Use Courts - Creekside Courts: The new multi-use outdoor court facility in Kin Park was open for play as of Wednesday, August 23, 2023. An engagement session was held on September 15, 2023. At the September 9, 2024 Council Meeting, Council approved the naming of the facility as "Creekside Courts". A grand opening ceremony was held on September 25, 2024 and the project is now complete.
  • Kin Park Trail Network Connections: Several new areas within Kin Park have been paved, connecting the new playground and the new multi-use sports courts to the existing trail network. Amenities such as bike racks, benches and tables were installed throughout the south side of Kin Park.
  • Memorial Arena HVAC: The Memorial Arena received a few updates internally, including the BAS HVAC units for heating and cooling the building. 
  • Memorial Arena Pad Replacement: The Memorial Arena Pad underneath the ice was replaced in summer of 2024. Heat floor loops were installed and pressure tested, dasher boards were replaced, and repairs and maintenance were performed on the ice plant. 
  • Rotary Park Playground Upgrade: Contractors broke ground at the Rotary Park playground site in September 2023 and 90% of the playground equipment was installed before the 2023/2024 winter season. By July 2024, the playground construction and landscaping was complete. The new playground was opened for play as of July 15, 2024.

Road Works, Streetlights and Utilities

  • 109 Avenue from 15 Street to 17 Street: Paving of 109 Avenue from 15 Street to 17 Street, including underground utility work, was completed in summer of 2024 and this project is now complete.

  • Camarlo Subdivision Phase 3 Road Rebuild, Drainage Upgrades and Streetlights: The third phase of the Camarlo Subdivision paving project, which included water and sewer upgrades, started in May 2024. The project moved along quickly and the road in the Camarlo Subdivision has now been paved, with landscaping and hydroseeding completed.Downtown Traffic Lights: Staff worked with contractors to replace the downtown traffic lights located at 102 Avenue and 103 Avenue on 10 Street. The lights were in need of some care and attention for some time, and Staff were excited to see this project on the roster for the summer of 2024. The project included:

    • Traffic light pole replacements
    • New accessible ramps
    • Bricks removed, new brushed concrete surface at corners
  • Parkhill Transmission Main Water Line: Crews completed the highway crossings and CN Rail bore crossing required for the Parkhill Transmission Main Water Line. This project was completed in October 2024. 
  • Sanitary Trunk Main Flushing: Flushing of the Sanitary Trunk Main across the City was completed in August. Flushing the main is necessary for regularly upkeep and maintenance of the line. After the flushing, the pipe is cctv’d with a camera to identify any problems areas or issue of concern for future addressing. 

  • Ball Diamond Upgrades
  • Christmas Decoration Upgrades Phase Two
  • Kin Park Multi-Use Outdoor Courts
  • NAR Park and Visitor Centre Lights
  • South Peace Multiplex Building Upgrades and Parking Lot Lights Structural Assessment
  • 14 Street from 102 Avenue to Alaska Avenue Streetlights
  • 17 Street Water Main Repair
  • 95 Avenue from 13 Street to 17 Street Road Rebuild, Drainage Upgrades and Streetlights
  • 96 Avenue from 8 Street to 13 Street Streetlights
  • 102 Avenue Bridge Slope Repair Work 
  • 106 Avenue from 6 Street to 8 Street Sanitary Trunk replacement
  • Arena Water Main Extension
  • Camarlo Subdivision Phase 2 Road Rebuild, Drainage Upgrades and Streetlights

  • 96 Avenue road work from 13 Street to 17 Street
  • Camarlo subdivision road work from 89 Avenue to 20A Street

  • 8 Street Frontage Road from 116 Avenue to 122 Avenue 
  • 8 Street Creek crossing replacement
    • Please note, this was a Ministry of Transportation project, not a City of Dawson Creek project. Questions or concerns may be directed to the Brocor office at 250-782-3404.
  • 10 Street from 92 Avenue to 94 Avenue
  • 10 Street from 110 Avenue to 112 Avenue
  • 13 Street from Alaska Avenue to 102 Avenue

  • 15 Street from 96 Avenue to Alaska Avenue
  • 17 Street from 89 Avenue to 210 Road
  • 102 Avenue Creek crossing replacement

Contact Us

The City of Dawson Creek
10105 - 12A Street
City of Dawson Creek, BC V1G 3V7
Telephone: 250-784-3600